Construction steps |
1.Remove the oil and dust from the substrate. |
2. According to the construction plan formulated by the technical department, perform rust prevention, rust removal or anti-corrosion treatment; if the materials of the tank and pipeline are different and there is rust, a rust-proof layer should be applied. |
3. According to the construction plan requirements, apply 1MM coating by spraying to achieve the desired thickness and overall appearance. |